After more than a thousand corrective actions and the rigorous verification work of each one, the Antonio Guiteras thermal power plant in this city of Matanzas will conclude the scheduled maintenance next Sunday, and will begin the complex synchronization start-up process.
Engineer Rubén Campos Olmos, general director of the Yumurino block, offers his considerations in a climate of realism, since he draws attention to the fact that each action must be properly tested and there is always the possibility of the occurrence of difficulties that are solved during the boot process.
Thus, it is expected that during Monday the 18th, the moment in which the startup process begins, the unit will be able to generate no less than 270 megawatts and remain online for longer. The plant's conservation program requires another much shorter intervention to guarantee generation during the summer and the most aspirational one in October, Capa, according to design and studies, to keep it at 280 MW stable for at least 45 days.
(Taken from the profile of journalist José Miguel Solís)
- You should not use obscene or offensive words.
- Comments should be related to the topic.
- Comments that violate previous policies will not be posted.